Project Updates

The City of Paris Public Works Department, in partnership with Delta Contracting, has begun a citywide street improvement project to mill and pave selected streets. Work began on July 28, 2025, and will continue until all scheduled streets are complete. This page will serve as the central hub for project updates.

Monday, September 29: Paving in progress on Glendale, Belmont, and Carroll Streets!

Drivers should expect temporary lane closures and possible delays in active construction areas. Residents are asked to avoid parking on streets where work is underway to allow crews full access.

Below is an interactive map showing the streets included in the project. Streets are color-coded as follows: Green – Complete, Yellow – In Progress, Orange – Upcoming.

  • Volunteer Dr ✅
  • Powell St ✅
  • Adkins St ✅
  • Porter St ✅
  • Forrest Heights Rd ✅
  • Sparks St ✅
  • South Market St ✅
  • Grove St ✅
  • McAdoo St ✅
  • Virginia St ✅
  • Madison St ✅
  • Dale St ✅
  • Blanton St ✅
  • Ogburn St ✅
  • Pine St ✅
  • Pierce St ✅
  • Glendale St
  • Belmont St
  • Carroll St
  • Bode St ✅
  • Vance St ✅
  • Link St ✅
  • Rider St ✅
  • Travis St ✅
  • Cherry St ✅
  • Jones St ✅
  • Lee St ✅

We appreciate the community’s patience as we make these important infrastructure improvements. Please check back regularly for the latest updates and scheduling information.

Questions? Contact the Public Works Department at 731-642-0473.